PT Petrolog Indah supported the 2025 turnaround at PT Kaltim Parna Industri, with the scope of work as follows:
1. Replaced 180 catalyst tubes, including their accessories (hairpins).
2. Performed supporting work for catalyst tube replacement, including scaffolding installation, insulation removal and installation, rigging and lifting, opening and closing manhole covers, touch-up painting, cutting and re-welding plates in the tube support area, and other necessary work.
3. Provided 30-ton and 250-ton capacity cranes for lifting activities throughout the work process.